95% built: can the Kinguélé Aval dam end Libreville’s blackouts?

Gabon’s government is counting on a new hydropower plant to bring relief to its capital, where power cuts have become a daily frustration.

The announcement

At a Council of Ministers meeting on 8 October, chaired by President Brice Clotaire Oligui Nguema, the government said the Kinguélé Aval hydropower plant was entering its final phase. According to Gabon Media Time:

  • Construction is 95 percent complete.
  • Capacity is about 35 megawatts (MW).
  • Timing: after connection to the national grid, the plant’s three turbines are due to start one after another between October and December 2026.
  • Impact: once fully running, the government says it will supply more than half of the electricity consumed in Greater Libreville and stabilise supply in the north-west of the country.

Operations still require two administrative authorisations, which have been submitted.

Where it is

Kinguélé Aval is on the Mbei river, downstream of existing dams at Kinguélé and Tchimbélé, which have supplied Libreville for decades. Building a new plant on the same river makes use of water already regulated by the upstream reservoirs.

Libreville’s reliance on floating power plants

Libreville currently relies heavily on thermal power, including floating power plants operated by Turkey’s Karpowership, which are costly and have been the subject of payment disputes. Hydropower, once built, is much cheaper to run and does not depend on imported fuel.

Gabon has large untapped hydropower potential. Other projects are being developed, including a planned plant of nearly 400 MW at Booué, with partners including the International Finance Corporation and EDF.

A note of caution

The government’s claim that a 35 MW plant will provide more than half of Greater Libreville’s electricity will depend on actual demand and how reliably the plant runs, particularly in dry months. Previous timelines for the project have slipped: the first tests had been expected in March 2026.

New generation also needs a reliable grid. Many of Libreville’s cuts are caused by problems in the distribution network, which a new dam will not fix on its own.

Turbines on, load-shedding down?

  • The start of each turbine before the end of the year.
  • Whether load-shedding in Libreville falls in early 2027.
  • Progress on larger projects such as Booué.

Sources: Gabon Media Time, 9 October 2026; Gabonactu; Gabon Flash Info; Conjonctures.

Top photo: The Libreville estuary. The new dam is meant to supply more than half of Greater Libreville’s power (file photo). Photo: VIGNA christian, Wikimedia Commons, CC BY-SA 4.0

Get Africa's top stories every morning

One email a day with the latest from Fifty4 News, covering news from all 54 African countries. Free, and you can unsubscribe at any time.

We don't spam. Read our privacy policy for more info.

Leave a Reply

Your email address will not be published. Required fields are marked *