The Accra–Kumasi expressway, a year on: cleared land, money in the bank, no contractor yet
A year ago this week, Ghana’s government announced a new Accra–Kumasi expressway in its 2026 budget: a 198.7km, six-lane toll road between the country’s two biggest cities. Twelve months on, the land has been cleared and money has been set aside, but no contractor has been chosen and building has not started.
What has been done
- The route is cleared. Soldiers of the Ghana Armed Forces’ 48 Engineer Regiment cleared a 175.6km right-of-way. It was formally handed over on 14 September at Kwaso, near Ejisu, Graphic Online and Citi Newsroom reported.
- Compensation was due to start. Finance Minister Cassiel Ato Forson said in May that payments to people who lost land and crops would begin in June, after assessments by state agencies, Citi Newsroom reported. Amounts have not been published.
- The money is set aside. President John Mahama said US$2 billion was in a special account at the Bank of Ghana, raised from domestic revenue. “We have not gone to borrow money from anywhere,” he said on 14 September, according to Citi Newsroom.
The total cost is less clear. An estimate of US$1.7 billion earlier this year rose to US$2 billion, SBM Intelligence noted, and 3News reported that the President spoke of the fund rising to US$4 billion by the end of the year. Forson has said the full amount will be in place by 31 December.
What has not happened yet
- No contractor. Firms were invited to apply for pre-qualification on 11 September. On 29 September, Roads Minister Kwame Governs Agbodza dismissed reports that a contract had been awarded. “We are going through a process of procurement; we haven’t even done halfway,” he said, 3News reported. The government expects to award the contract before the end of 2026.
- No sod-cutting. Mahama promised to return to Kwaso before Christmas to cut the sod, calling it “a special Christmas present for Nananom and this nation”, Graphic Online reported.
What the road promises
According to the government’s plans, as reported by Graphic Online:
- six lanes over 198.7km, through the Greater Accra, Eastern and Ashanti regions
- a journey of about two hours, down from five to six hours today
- two toll interchanges, eight interchanges serving towns on the route and four rest stops
- CCTV cameras to catch reckless driving, and space set aside for a future railway
Why the new road matters
Safety on the existing highway is one reason the road matters: crashes on Ghana’s roads killed 2,949 people in 2025, the highest toll in 35 years, SBM Intelligence noted. But the firm also warned of the cost to other spending, pointing out that the agriculture ministry’s allocation for 2026 was cut by 54 percent. “The project tests whether the government can combine non-debt infrastructure financing with fiscal consolidation,” it wrote.
The budget and the expressway
- Thursday, 12 November: how much the 2027 budget sets aside for the expressway, and whether it confirms the total cost.
- The contract award: which company or companies win the contract, and at what price. The government expects to award it before the end of 2026.
- 31 December: the date Forson set for the full funding to be in place.
- Before Christmas: whether the President returns to Kwaso to cut the sod, as promised.
- Compensation: whether the government publishes how much has been paid, and to how many people.
- Tolls: what drivers will pay. We have not seen toll rates published.
Fifty4 News will return to the story as these milestones arrive.
Sources: Graphic Online, 14 September 2026; Citi Newsroom, 14 September 2026; Citi Newsroom, 28 May 2026; 3News, 29 September 2026; MyJoyOnline, 14 September 2026; SBM Intelligence, 18 September 2026.
Top photo: Road works at the Pokuase interchange on the existing Accra–Kumasi highway (file photo, 2020). Photo: Amuzujoe, Wikimedia Commons, CC BY-SA 4.0